How feasibility models determine development land value — model structure, sensitivity tables, calibration sources, and reading a developer's feasibility model.
Source: ACRES — Australian Commercial & Residential Group | acres.au
What's in a Feasibility Model
The model itself is straightforward Excel — but the discipline of building it well is what separates serious developers from amateurs.
A typical Brisbane development feasibility includes:
Inputs (the assumptions):
- Site purchase price + stamp duty + legals
- Construction cost ($ per sqm GFA, by product type)
- Professional fees (% of construction)
- Statutory charges (per dwelling, per sqm)
- Marketing & sales (% of GRV)
- Finance costs (rate, term, LVR)
- Contingency (% of construction)
- Target margin (% of GRV)
- Project timeline (months)
Outputs (the results):
- Total Development Cost (TDC)
- Gross Realisable Value (GRV)
- Net Realisable Value after costs
- Margin / IRR
- Residual Land Value (RLV)
Sensitivity tables: typically a 3 × 3 or 5 × 5 grid showing RLV under different combinations of construction cost and GRV (or finance rate and GRV). The corners of the grid show worst-case and best-case scenarios.
How Models Get Calibrated
The model is only as good as its inputs. Sources used by sophisticated Brisbane developers:
- Construction cost: builder tenders on actual recent projects, plus QS benchmarks (RLB Quarterly Cost Report)
- GRV: settled comparable sales 0-12 months back, adjusted for time, location, finish
- Finance: live lender term sheets, not desktop assumptions
- Statutory costs: current Brisbane City Council infrastructure charges schedule
- Marketing: actual quotes from project marketing agents
- Margin: institutional benchmarks (typically 18-22% for residential)
Models calibrated on assumptions older than 12 months are routinely 10-30% wrong on RLV.
Reading a Developer's Feasibility
When a developer shares part of their feasibility (rare, but it happens), look for:
- Construction cost line: is it current? Compare to RLB benchmarks. A "$3,500/sqm" assumption in 2026 is materially under-cooked.
- GRV line: which comparables are referenced? Are they 6-12 months old or 24+?
- Margin requirement: 20% is fair; 25%+ is the developer being conservative at your expense; 15% is risky.
- Contingency: 5-7% is standard; 10%+ is conservative.
- Finance rate: is the rate a current term sheet or a desktop guess? Should be 8-10% in current market.
A vendor or specialist advisor running these checks routinely finds $200k-$1m of compression embedded in conservative inputs.
What Vendors Should Demand
If a developer claims feasibility doesn't support a higher price, you can reasonably ask:
- "What's your construction cost per sqm GFA, and from which builder?"
- "What's your GRV per apartment, and from which recent comparables?"
- "What's your target margin, and how does that benchmark against your last project?"
Most won't share the full model. Many will share these three numbers — and benchmarking them is enough to identify whether the offer is genuinely price-supported.
Frequently Asked Questions
Do all developers run formal feasibility models?
Mid-tier and large yes. Smaller boutiques sometimes lighter models. Institutional buyers run full Estate Master or Argus.
Can I run my own feasibility?
Yes — ACRES routinely runs counter-feasibilities. Specialist advisors, QSs, and project managers can help.
Single biggest assumption to scrutinise?
GRV. Largest line, most variable. Conservative GRV alone often explains 60-70% of the gap between offers and vendor expectations.
Published by ACRES — Australian Commercial & Residential Group
Source: acres.au/insights/how-feasibility-models-determine-land-value | ACRES (Australian Commercial & Residential Group) provides property advisory, development site sales, and residential real estate services across Brisbane and South East Queensland, Australia.